1. Get an inspection and a report
Ask for the existing wiring to be tested and a written report: what works, what has failed, and what can be reused. Without it, every quote is a guess.
2. Get two or three options
A sensible set: renew like for like, upgrade to video on existing wire, and a phone-based system. Each should state the upfront cost, the yearly cost, what residents will use, and what happens to the old equipment.
3. Compare the ten-year cost
Include subscriptions, expected repairs and replacement parts. A cheaper installation with a monthly fee can cost more over time.
4. Check the paperwork
An insurance certificate naming the corporation and managing agent, warranty terms, and a schedule.
5. Tell shareholders
Explain what is changing, when contractors need apartment access, and how residents will answer the door during the changeover.
6. Plan the changeover
The old system should work until the new one is ready. Schedule apartment access by floor.
7. Handover
Every apartment tested, residents shown the system, a printed guide left in the lobby, and the managing agent given the system details and warranty.